The steels arrived this afternoon. There were a few complications, starting with the driver refusing to use the crane to lift them to the roof because I had only paid for delivery and not crane use. Despite having asked for it, it wasn't on the paperwork so I had to go to the cashpoint so that they could be craned up. They are seriously heavy - no other way to get them up there, but with some heavy lifting from Ivan and Nick on the scaffold, they were soon in the loft space.
|
The expensive crane (and Dimitri!) in action |
|
Ivan and Nick never stop working |
The site looks very different to my last visit, for a start the upstairs
bathroom is no longer there. The guys stripped out the bath, basin and
loo, then stripped the walls of the lath and plaster, before removing the
walls completely. All of the rotten plaster in my bedroom has been
removed back to bare brick and the plaster has been taken off the lath
in the hall. We really will be starting again from scratch but the new
walls will be perfectly solid and straight.
|
No bathroom and very little plaster left. A blank canvas |
|
The first floor passage minus plaster |
|
Wide open |
Whilst stripping the plaster in the passageway the guys have been finding old paperwork, letters and invoices, all dated in the 1890s. I didn't have a lot of time to look through them but it will be interesting to have a look at them in more detail.
|
Ivan finds another letter behind the lath |
|
This one's dated 1897 |